8:30 – 8:40 |
Opening Remarks |
Dr. Wayne Clough |
8:40 – 8:50 |
Introduction of Panel Members |
Panel |
8:50 - 9:00 |
Charge and Objectives |
Greg Giornelli |
9:00 – 9:50 |
Atlanta’s CSO System Problem |
John Griffin |
|
- Background and history of Atlanta’s CSO System |
|
|
- Regulatory issues and national CSO policy |
|
10:00 – 10:30 |
Press Conference |
Mayor Franklin
Dr. Wayne Clough |
10:30 – 12:00 |
CSO Remediation Program |
|
|
- CSO Consent Decree |
Mitchell Griffin |
|
- Public Concerns |
|
|
- Authorized CSO Remedial Measures Plan |
|
|
- Predesign |
Joseph Basista |
|
- Plan Refinement |
|
|
- Affordability Analysis |
|
|
- Stormwater Management |
|
|
- Next Steps |
|
12:00-1:00 |
Lunch |
|
1:00-2:30 |
Tour of Atlanta CSO Facility |
|
2:30-3:00 |
Charge & Objectives: Reassessment,
Goal-Setting |
Dr. Clough & Panel |
3:00-3:30 |
Additional Information Needs |
Panel |
|
- Briefings/Data/Resources |
|
3:30-4:00 |
Future Meeting Dates/Logistics |
Panel |
Adjournment |
|
|
Location: Georgia Center for Advanced Telecommunications Technology
|
|
|
|
|