Drinking Water
The City entered into a Drinking Water Consent Decree agreement
with the Georgia Environmental Protection Division (EPD) in December
1997. The decree alleges that the City’s drinking water
facilities violated certain provisions of the Safe Drinking Water
Act. Specifically, EPD inspections revealed that the City did
not comply with these requirements:
- Continuous recording of disinfectant residual from treatment operations
- Retention of certain water system records, including nitrate and fluoride monitoring results
- Complete monitoring of corrosion control measures
- 24-hour staffing by certified personnel
- Permitting of all outfalls
- Complete and accurate completion of records and reporting forms
In addition, there were incidents of discharges from the City’s facilities that did not comply with permits.
The Bureau of Water had already undertaken some corrective measures
at the time the Consent Decree was executed. The Decree lays out additional
steps the Bureau must take to remain in compliance, including increased
staffing, sample collection and more stringent reporting. The proposed
capital improvement plan will enable the Bureau of Water to permanently
eliminate all unpermitted discharges other than storm water from its
treatment plants.
Bureau of Drinking Water
Droplets Newsletter
Bureau of Water 2003 Capital Improvement Projects
|
Consent Order & Regulatory |
$54 M |
Reliability and Operational |
$42 M |
Atlanta/Fulton Co. WTP Phase 2.5 |
$35 M |
Total 2003 Capital Projects |
$131 M |
Total Long-Term CIP (through 2014) |
$700+M |
For further information, contact Chris New @ 404-330-6081.
|