Clean Water Atlanta Home Logo
CLEAN WATER ATLANTA OVERVIEW DRINKING WATER WASTE WATER
sub_main_top_right
sub_main_middle_left sub_main_middle_right
sub_main_bottom_left sub_main_bottom_right
consent decree program management
stormwater
wq monitoring
sanitary sewer overflow
combined sewer overflow

News Releases

 
Advanced Search
 
 
MAYOR’S OFFICE OF COMMUNICATIONS
55 Trinity Avenue, Suite 2500
Atlanta, Georgia 30303
   
CONTACT: Sandra Allen Walker, Director
Office 404-330-6395
Cell: 404-925-1666
E-mail: swalker@ci.atlanta.ga.us
  or
  LaChandra Butler
Office: 404-330-6248
Cell: 404-886-2334
E-mail: ldbutler@ci.atlanta.ga.us
 
December 5, 2003

Text of Watershed Management Commissioner Jack Ravan's Letter to EPA and EPD

CORRECTED VERSION (12/5/03) December 4, 2003

VIA FACSIMILE AND CERTIFIED MAIL RETURN RECEIPT REQUESTED

Chief, Water Programs Enforcement Branch Water Management Division U.S. Environmental Protection Agency, Region 4 Atlanta Federal Center 61 Forsyth Street, S.W. Atlanta, Georgia 30303 ATTN: Douglas Mundrick

Georgia Environmental Protection Division Permitting, Compliance, and Enforcement Program 4220 International Parkway, Suite 101 Atlanta, Georgia 30354 ATTN: Marzieh Shahbazaz

Subject: Notice of Delay to EPA and EPD Consent Decree - City of Atlanta First Amended Consent Decree - City of Atlanta Civil Action File No. 1:98-CV-1956-TWT

As required under Section XII, Force Majeure (C), of the Consent Decree (CD) and First Amended Consent Decree (FACD), the City of Atlanta submits this notice of events arising from actions by the Atlanta City Council on December 1, 2003 that will delay or prevent the performance of its obligations under the CD and FACD, despite the City's best efforts to fulfill these obligations. As required, this notice is submitted within fifteen (15) days after the City has learned or should have learned of the delay or anticipated delay. The potential delays are both capital and compliance in origin. This letter sets forth precipitating events for potential delays, the nature of the delays and the proposed plan of action to cure the delays.

On Monday, December 1, 2003, the Atlanta City Council approved a water and sewer rate increase ordinance and a Department of Watershed Management (DWM) budget ordinance. These ordinances differed significantly from the proposed rate increase and budget requests put forward by the City's administration as a component part of meeting the terms and conditions of the Consent Decrees. Specifically, the approved rate increase ordinance, 03-O-1713, substantially diminished the effective rate increase sought of 45% for FY 2004 by providing an "affordability base rate" exemption of six hundred cubic feet per month for all customers at the current rate. In addition, the budget ordinance cut $25 million from the DWM operations budget for 2004.

One immediate consequence of the ordinances passed by City Council is the inability of the City to issue new bonds in 2004. The six hundred cubic feet rate structure as passed by the Council undermines the financial strength and stability of the water and wastewater fund. Specifically, it results in a revenue loss of $25 million in the first year which compounds to over $75 million by the fifth year and also results in a declining debt coverage ratio. Consequently, this rate structure does not provide for a solid five year financial plan or revenue stream that can adequately demonstrate to Wall Street that the City can support any future borrowing. Absent the necessary revenue generated by issuance of new bonds, the City will be unable to meet the capital needs anticipated for the coming fiscal year. Therefore, under the current capital projects schedule, the City will not be able to initiate new consent decree projects beginning in July 2004.

In addition to failing to meet this calendar, there is a more immediate compliance impact. The lack of funding will require the City of Atlanta to prioritize its capital projects with an emphasis on the provision of basic drinking water and sewer service and the protection of public health over consent decree compliance. The effect will be that we will not initiate consent decree compliance projects that were scheduled as early as January 2004.

A specific failure is the West Area Tunnel project. Set forth below is the proposed schedule for West Area Tunnel completion:

Activity Date Float CD Milestone Complete Design Jan. 2, 2004 0 Jan. 2, 2004 BOP Advertises Constr. Jan. 2, 2004 37 None

DOP Receives Bids Mar. 17, 2004 0 None

Contractor NTP June 21, 2004 21 Jul. 12, 2004 Substantial Completion Nov. 3, 2007 4 Nov. 7, 2004

However, given the City Council's actions, we will be unable to meet this schedule. The City would have started the bid process, which would have included the advertisement and the release of bid plans, on January 2, 2004. This schedule would have provided 62 days of float through the final construction deadline. Due to the revenue constraints to completing this project, the City will be unable to even advertise the project or to go forward with the Tunnel project in any meaningful form.

A third major area of potential delay, also precipitated by the City Council's approved rate increase, is that the revenue stream will not provide adequate financial resources for the Renewal & Extension Fund. This means that the $30 million worth of smaller capital repair and system improvement projects will not be performed as required.

The fourth major area of potential delay is precipitated by the budget ordinance. The financial analysis conducted by DWM of the approved budget indicates that the budget will not provide the funding necessary to meet the compliance, capital project and operational requirements under the two Consent Decrees. The City Council's approved budget ordinance reduces the Department of Watershed Management's budget by $25 million for 2004. The effects of this budget reduction include the fact that the City will not be able to adequately fund the required management, operation and maintenance systems as required under the Consent Decrees. In addition, we will not be able to fund the management system improvements that we have recently committed to in our Indian Creek report and presentation. The conditions that led to the construction failure at Indian Creek, including inadequate funding and delays in project initiation, will not be corrected but will be further exacerbated under the City Council's approved ordinances.

Absent action by the City Council to approve adequate funding and to rescind substantial cuts to the DWM operational budget, the City cannot in good faith offer a plan of proposed compliance.

Thank you for your consideration of this notification. If you require additional information, please let us know or call me at (404) 330-6522.

Sincerely,

Jack Ravan
Commissioner of Watershed Management
City of Atlanta

 
HOT PROJECTS
HOT TOPICS
 
Copyright 2007 City of Atlanta, Depart of Watershed Management. All rights reserved
legal statement
privacy
disclaimer
site statistics