Objective: Rehabilitate 2% of Total System (1450
Miles) Per Year
Performance Goal: Rehabilitate 2% of System per
yesr = 28.8 miles per year = 2.4 Miles per month through December
2006
Report Date: March 2006
|
Miles
of Sewer Rehabilitated |
|
Monthly
|
Cumulative |
Monthly |
Cumulative |
Month |
Goal |
Goal |
Performance |
Performance |
Jan |
2.4 |
2.4 |
1.7 |
1.7 |
Feb |
2.4 |
4.8 |
3.3 |
5.0 |
Mar |
2.4 |
7.2 |
3.5 |
8.5 |
Apr |
2.4 |
9.6 |
|
|
May |
2.4 |
12.0 |
|
|
Jun |
2.4 |
14.4 |
|
|
Jul |
2.4 |
16.8 |
|
|
Aug |
2.4 |
19.2 |
|
|
Sep |
2.4 |
21.6 |
|
|
Oct |
2.4 |
24.0 |
|
|
Nov |
2.4 |
26.4 |
|
|
Dec |
2.4 |
28.8 |
|
|
Rehabilitation (Relining) Methods:
- Open Cut Replacement
- Cured-in-Place Pipe (CIPP) Relining of Existing Pipe
- Gunite Lining of Existing Large Diameter Concrete Pipe
- HDD Horizontal Directional Drilling
Note--
Rehab contracts for Sewer Group 1 will be initiated within 2005,
which will further increase production
|