CSO Tunnels Project Schedule

West Tunnel

1.
Notice to Proceed
April 2003
 
2.
Mobilization and site preparation:
July 2003
(includes site-specific work such as:  
  • Moving in and setting up staff ande crew facilities (trailers)
  • Moving in heavy equipment (front end loaders, backhoes, etc.)
  • Erecting silt fences, other erosion and sediment control measures
  • Clearing and grubbing)
  • Pre-blast survey and monitoring
     
    Easements and land acquisitions as required (design of alignment confines easements and acquisitions to commercial or vacant properties where possible)
     
    3.
    Shaft Construction - (8-10 months)
    May 2004
     
  • Truck traffic as rock and soil are removed and hauled away
  • Very little noticeable construction activity on the site
    (most work is underground)
  • Occasional blasting
  • Shafts are the main point for material entry and exit
  •  
    4.
    Install Tunnel Boring Machine and begin boring (18-20 months)
    January 2005
     
     
    Milestone Completion Date for West Tunnel
    October 2007

    East Tunnel

    1. Notice to Proceed
    June 2004
       
    2. Mobilization and site preparation:
    Three Months
         
      (includes site-specific work such as:  
     
  • Moving in and setting up staff ande crew facilities (trailers)
  •  
  • Moving in heavy equipment (front end loaders, backhoes, etc.)
  •  
  • Erecting silt fences, other erosion and sediment control measures
  •  
  • Clearing and grubbing)
  •    
    3. Shaft Construction
    8 - 10 months
       
     
  • Truck traffic as rock and soil are removed and hauled away
  •  
  • Very little noticeable construction activity on the site
    (most work is underground)
  •  
  • Occasional blasting
  •  
  • Shafts are the main point for material entry and exit
  •    
    4. Install Tunnel Boring Machine and begin boring
    May 2005
    (18-20 months)
       
     
  • Very little noticeable construction activity on the site (most work is underground); however, may involve moving some of the construction activities to the next shaft location; shafts are the main point for material entry and exist.
  •  
  • No blasting
  •  
  • Truck traffic as rock and soil are removed and hauled away
  •  
  • Tunnel is lined as you go
  •  
    Milestone Completion Date for East Tunnel
    January 2007