CSO Tunnels Project Schedule
|
West Tunnel
1. |
Notice to Proceed |
April 2003 |
|
|
|
2. |
Mobilization and site preparation: |
July 2003 |
|
(includes site-specific work such as: |
|
|
Moving in and setting up staff ande crew
facilities (trailers) |
|
Moving in heavy equipment (front end loaders,
backhoes, etc.) |
|
Erecting silt fences, other erosion and sediment
control measures |
|
Clearing and grubbing) |
|
Pre-blast survey and monitoring |
|
|
|
Easements and land acquisitions as required (design
of alignment confines easements and acquisitions to commercial
or vacant properties where possible) |
|
|
3. |
Shaft Construction - (8-10 months) |
May 2004 |
|
|
|
Truck traffic as rock and soil are removed
and hauled away |
|
Very little noticeable construction activity on the site
(most work is underground)
|
|
Occasional blasting
|
|
Shafts are the main point for material entry and exit
|
|
|
|
4. |
Install Tunnel Boring Machine and begin boring (18-20 months) |
January 2005
|
|
|
|
|
|
Milestone Completion
Date for West Tunnel |
October
2007 |
East Tunnel
| 1. |
Notice to Proceed |
June 2004 |
| |
|
|
| 2. |
Mobilization and site preparation: |
Three Months |
| |
|
|
| |
(includes site-specific work such as: |
|
| |
Moving in and setting up staff ande crew
facilities (trailers) |
| |
Moving in heavy equipment (front end loaders,
backhoes, etc.) |
| |
Erecting silt fences, other erosion and sediment
control measures |
| |
Clearing and grubbing) |
| |
|
| 3. |
Shaft Construction |
8 - 10 months |
| |
|
| |
Truck traffic as rock and soil are removed
and hauled away |
| |
Very little noticeable construction activity on the site
(most work is underground)
|
| |
Occasional blasting
|
| |
Shafts are the main point for material entry and exit
|
| |
|
|
| 4. |
Install Tunnel Boring Machine and begin boring |
May 2005
(18-20 months) |
| |
|
| |
Very little noticeable construction activity
on the site (most work is underground); however, may involve
moving some of the construction activities to the next shaft
location; shafts are the main point for material entry and
exist. |
| |
No blasting |
| |
Truck traffic as rock and soil are removed
and hauled away |
| |
Tunnel is lined as you go |
| |
| Milestone Completion Date for East Tunnel |
January 2007 |
|