East Area CSO Tunnels Project Schedule
|
| 1. |
Notice to Proceed |
June 2004 |
| |
|
|
| 2. |
Mobilization and site preparation: |
Three Months |
| |
|
|
| |
(includes site-specific work such as: |
|
| |
Moving in and setting up staff ande crew facilities (trailers) |
| |
Moving in heavy equipment (front end loaders, backhoes, etc.) |
| |
Erecting silt fences, other erosion and sediment control measures |
| |
Clearing and grubbing) |
| |
|
| 3. |
Shaft Construction |
8 - 10 months |
| |
|
| |
Truck traffic as rock and soil are removed and hauled away |
| |
Very little noticeable construction activity on the site
(most work is underground)
|
| |
Occasional blasting
|
| |
Shafts are the main point for material entry and exit
|
| |
|
|
| 4. |
Install Tunnel Boring Machine and begin boring |
May 2005
(18-20 months) |
| |
|
| |
Very little noticeable construction activity on the site (most work is underground); however, may involve moving some of the construction activities to the next shaft location; shafts are the main point for material entry and exist. |
| |
No blasting |
| |
Truck traffic as rock and soil are removed and hauled away |
| |
Tunnel is lined as you go |
| |
| Milestone Completion Date for East Tunnel |
January 2007 |
|